Colossus

xAI's Memphis-area campus: ~2 GW and 555,000 GPUs across Colossus 1 and 2 — the largest single-site AI installation, partly leased to Anthropic (all of Colossus 1) and Google (Colossus 2 capacity).

Relationships

xAI
  • dealAnthropic leases all of Colossus 1(facility ↔ lessor) May 6, 2026
  • dealGoogle leases Colossus 2 capacity(facility ↔ lessor) Jun 5, 2026
Anthropic
  • dealAnthropic leases all of Colossus 1(facility ↔ lessee) May 6, 2026
GoogleGOOGL
  • dealGoogle leases Colossus 2 capacity(facility ↔ lessee) Jun 5, 2026

Events

  • Anthropic leases all of Colossus 1

    Anthropic takes exclusive capacity at Colossus 1 for inference at $1.25B/month for three years, disclosed via SpaceX IPO filings.

    DEAL · May 6, 2026 · role: facility · confirmed

  • Google leases Colossus 2 capacity

    Google agrees to ~$920M/month (≈$30B through June 2029) for ~110,000 GPUs at Colossus 2, per SpaceX regulatory filing.

    DEAL · Jun 5, 2026 · role: facility · confirmed

Claims on record

  • As of May 2026, the Colossus 1 data center supported over 220,000 NVIDIA GPUs including H100, H200, and around 30,000 GB200 accelerators

    UNVERIFIED · Wccftech · Jul 19, 2026

  • The Colossus 2 data center currently has over 550,000 GPUs, divided between GB200 and GB300 accelerators

    UNVERIFIED · Wccftech · Jul 19, 2026

  • The Colossus campus reached roughly 2 GW of capacity with about 555,000 GPUs, making it the largest single-site AI installation.

    CORROBORATED · Tom's Hardware